The Louisiana Department of Transportation and Development (DOTD) Area Engineer, Robert W. Mays announced that work will begin today, July 29, to reconstruct the roadway on La. 377 from the Allen Parish Line to its junction with La. 10
The construction site will extend for approximately 2.6 miles.
The intent of this project is to reconstruct the roadway to stabilizing the base with cement and overlaying with two inches of asphaltic concrete along with aggregate shoulders.
Traffic will continue to travel on this roadway during reconstruction and should be completed in less than two months.
The project was awarded to W.E. McDonald and Son, LLC of Glenmora in the amount of $846,521.63.
The project engineer’s office administering this project is located at 598 Alexandria Hwy. in Leesville and can be reached at 337-238-6406.